Topic: Free PMP Exam Sample Question
Cornelius Fichtner

Member
Posts: 288

Reputation: 0
Free PMP Exam Sample Question
on: 16 April 2013, 14:19

The following PMPĀ® exam sample question is taken from the Free PMP Exam Simulator:

——————————

Your pharmaceutical drug manufacturing project is behind schedule and you are under pressure from the stakeholders to finish the project on time. In order to improve performance you want to use a schedule compression technique. You have four different tasks in your project that can be performed in parallel. Which schedule compression technique is best to use in this situation?

A.) Fast Tracking

B.) Crashing

C.) Applying Leads and Lags

D.) Resource Leveling

——————————

Hint: There are only two schedule compression techniques.

——————————

All our questions are updated to the latest PMBOKĀ® Guide standard. Stop by at http://free.pm-exam-simulator.com and try the PMP Exam Simulator free for 3 days. We also offer 110 free questions at http://www.free-pm-exam-questions.com. We are a PMI Registered Education Provider.

Please click here: http://www.facebook.com/questions/10150291138729970/ for the correct answer and explanation.

Until next time,

Cornelius Fichtner, PMP

President, OSP International LLC – http://www.project-management-prepcast.com

Pages: [1]

WP Forum Server by ForumPress | Lucid Crew
Version: 1.8.2;
Page loaded in: 0.015 seconds.

Comments are closed.

Creative Commons License
Project Management Insight is licensed under a Creative Commons Attribution-ShareAlike 3.0 Unported License.
Designed and hosted by InfoSer UK