Topic: Free PMP Exam Sample Question
Cornelius Fichtner

Member
Posts: 288

Reputation: 0
Free PMP Exam Sample Question
on: 8 May 2013, 06:31

The following PMPĀ® exam sample question is taken from the Free PMP Exam Simulator:

——————————

On a project, several risk response strategies may be used to effectively manage project risks. The strategy or mix of strategies should be determined when planning for risk responses. Which of the following statements best describes an Accept risk response strategy for negative risks or threats?

A) Adopting less complex processes

B) Purchasing insurance

C) Establishing Contingency Reserves

D) Extending the schedule

——————————

Hint: A risk acceptance strategy is adopted when it is impossible to eliminate all threats from a project. One of the answer choices is performed in the early stages of planning

——————————

All our questions are updated to the latest PMBOKĀ® Guide standard. Stop by at http://free.pm-exam-simulator.com and try the PMP Exam Simulator free for 3 days. We also offer 110 free questions at http://www.free-pm-exam-questions.com. We are a PMI Registered Education Provider.

Please click here: https://www.facebook.com/questions/10150295623474970/ for the correct answer and explanation.

Until next time,

Cornelius Fichtner, PMP

President, OSP International LLC – http://www.project-management-prepcast.com

Pages: [1]

WP Forum Server by ForumPress | Lucid Crew
Version: 1.8.2;
Page loaded in: 0.029 seconds.

Comments are closed.

Creative Commons License
Project Management Insight is licensed under a Creative Commons Attribution-ShareAlike 3.0 Unported License.
Designed and hosted by InfoSer UK